The new container building of the German School of Budapest

Bánáti + Hartvig Architects
/
Educational
/
Hungary
Company Name
Bánáti + Hartvig Architects
ARCHITECTURAL CREDITS
Bánáti + Hartvig Architects
Project Team
GENERAL CONSTRUCTION: Lakort kft.
SUPPORTING STRUCTURE: mdrs2 kft.
BUILDING SERVICE ENGINEERING: BS plan kft.
ELECTRICAL INSTALLATION: Artrea Consulting Kft.
FIRE SAFETY: OPTOMM Mérnöki Iroda Kft.
ACOUSTICS: ’95 APSZIS BT.
CLIENT/OWNER NAME:
Deutsche Schule Budapest Foundation
Project Name:
The new container building of the German School of Budapest
Company Country:
Hungary
Project Country:
Hungary
Project City:
Budapest
Project Category:
Educational
Project Area:
Brutto area: 393 m2 (with the main building in total: 11.688 m2)
Completion Date:
20231129
Project overview
The German School of Budapest had to expand quickly for the new school year. The solution was to redevelop an existing container building, boosting capacity and architectural quality without harming the environment. The terrace was designed to avoid nearby trees. To minimize CO2 emissions, the new structure reused the container’s original columns and used minimal concrete. Designers calculated that building with reinforced concrete would emit enough CO2 to require 101 trees 100 years to offset.
Project history
2022 september – request for an additional floor extending the existing container building.(After that they reaised that the container-constructer’s team itself can not provide the expected design.)2022 november – concept plan, and cost calculations based ont he plans.Due to the given structural capabilities, it turned out to be better to rebuild than to use reinforcements. In this case the layout was less effected by the existing situation. So, redisign started.2023 january – new concept2023 march – permit plans, – may: permit2023 may – construction plan2023 june – november – execution phase